+92 300 5584929

2 Kanal house construction cost

Estimate what your house will cost to build, and where the money goes.

What to build
Materials
Rooms

The usual number for this size is already in the estimate.

Good materials and the finishes most homes use.

Estimated cost

PKR 6.3 Crore

PKR 5,000 per Sq. Ft. · 12,600 Sq. Ft. covered

Grey structure materials
PKR 3.02 Crore
Finishing materials
PKR 2.21 Crore
Labour
PKR 1.07 Crore

A guide for planning, not a quote. Rates last updated 3 November 2026.

Where the money goes

A typical split, which your design and materials will change

Foundation and structure
PKR 3.17 Crore · 50.3%
Wood, metal and tile works
PKR 1.94 Crore · 30.9%
Electrical works
PKR 58.97 Lakh · 9.4%
Plumbing works
PKR 35.78 Lakh · 5.7%
Fittings and fixtures
PKR 24.26 Lakh · 3.9%

Foundation and structure

PKR 3.17 Crore

The basic house: foundation, floors, walls, roofing and plastering.

  • Bricks, cement, sand and crush 1.98 Crore
  • Labour cost 59.6 Lakh
  • Excavation and steel reinforcement 54.43 Lakh
  • Roof insulation, termite and water proofing 4.54 Lakh

Wood, metal and tile works

PKR 1.94 Crore

Flooring, cabinets, wardrobes, windows and all metal work.

  • Tile work 79.38 Lakh
  • Labour cost 37.8 Lakh
  • Paint and ceiling works 35.28 Lakh
  • Wardrobes and cabinets 22.05 Lakh
  • Metal works 11.03 Lakh
  • Windows 8.82 Lakh

Electrical works

PKR 58.97 Lakh

Underground wiring and all electrical items.

Grey structure 19.28 Lakh · Finishing 39.69 Lakh

  • Wires and cables 22.05 Lakh
  • Switches and back boxes 14.18 Lakh
  • Lights, fans and chandeliers 11.03 Lakh
  • Conduits and accessories 7.56 Lakh
  • Labour cost 4.16 Lakh

Plumbing works

PKR 35.78 Lakh

Underground piping, water supply and drainage.

  • Pumps and drains 12.1 Lakh
  • Labour cost 5.54 Lakh
  • Drainage system piping 4.54 Lakh
  • Gas piping 4.54 Lakh
  • Cold and hot water supply 3.02 Lakh
  • UPVC pipeline for sewerage system 3.02 Lakh
  • AC drainage system 1.51 Lakh
  • Insulation Armaflex 1.51 Lakh

Fittings and fixtures

PKR 24.26 Lakh

Kitchen and bathroom accessories.

  • Bathroom 19.85 Lakh
  • Kitchen 2.21 Lakh
  • Geyser and manhole 2.21 Lakh
Foundation and structure
PKR 3.17 Crore · 85.2%
Plumbing works
PKR 35.78 Lakh · 9.6%
Electrical works
PKR 19.28 Lakh · 5.2%

Foundation and structure

PKR 3.17 Crore

The basic house: foundation, floors, walls, roofing and plastering.

  • Bricks, cement, sand and crush 1.98 Crore
  • Labour cost 59.6 Lakh
  • Excavation and steel reinforcement 54.43 Lakh
  • Roof insulation, termite and water proofing 4.54 Lakh

Plumbing works

PKR 35.78 Lakh

Underground piping, water supply and drainage.

  • Pumps and drains 12.1 Lakh
  • Labour cost 5.54 Lakh
  • Drainage system piping 4.54 Lakh
  • Gas piping 4.54 Lakh
  • Cold and hot water supply 3.02 Lakh
  • UPVC pipeline for sewerage system 3.02 Lakh
  • AC drainage system 1.51 Lakh
  • Insulation Armaflex 1.51 Lakh

Electrical works

PKR 19.28 Lakh

Underground wiring and all electrical items.

  • Conduits and accessories 7.56 Lakh
  • Switches and back boxes 7.56 Lakh
  • Labour cost 4.16 Lakh
Wood, metal and tile works
PKR 1.94 Crore · 75.2%
Electrical works
PKR 39.69 Lakh · 15.4%
Fittings and fixtures
PKR 24.26 Lakh · 9.4%

Wood, metal and tile works

PKR 1.94 Crore

Flooring, cabinets, wardrobes, windows and all metal work.

  • Tile work 79.38 Lakh
  • Labour cost 37.8 Lakh
  • Paint and ceiling works 35.28 Lakh
  • Wardrobes and cabinets 22.05 Lakh
  • Metal works 11.03 Lakh
  • Windows 8.82 Lakh

Electrical works

PKR 39.69 Lakh

Underground wiring and all electrical items.

  • Wires and cables 22.05 Lakh
  • Lights, fans and chandeliers 11.03 Lakh
  • Switches and back boxes 6.62 Lakh

Fittings and fixtures

PKR 24.26 Lakh

Kitchen and bathroom accessories.

  • Bathroom 19.85 Lakh
  • Kitchen 2.21 Lakh
  • Geyser and manhole 2.21 Lakh
Share this estimate
Link copied

Popular sizes

Double storey, at standard quality, with material

Questions about building costs

What is included in a grey structure?

The basic build: foundation, columns, beams, roof, walls, plaster, and the pipes and conduits inside them. It leaves out tiles, paint, doors, kitchens, bathrooms, lights and other finishes.

What is covered area?

The total floor space you build across all floors, including the walls, as opposed to the plot size. Costs follow covered area, which is why a two-storey house costs about twice a one-storey one on the same plot. We assume a usual figure, which you can change to match your plan.

With material or without material?

With material, the contractor supplies everything and the estimate covers materials and labour. Without material, you buy the materials yourself and the estimate covers labour only, so you still need to budget for materials.

How accurate is this?

It is a guide for planning, not a quote. Your design, soil, basements, boundary walls, material prices and the contractor all move the real cost. For a real budget, get a detailed estimate from a contractor.

How do the rooms change the cost?

We start from the rooms a house of that size usually has, which the rates already allow for. One more or fewer changes the items it touches: another bathroom adds its fittings, walls, a window and lighting, while another kitchen adds cabinets too. Plumbing, wiring and tiles here follow the covered area instead.

What does it leave out?

The plot itself, approval and design fees, a basement, boundary walls, solar, air conditioners and furniture, unless your contractor includes them.

Where do the rates come from?

Our team sets them and updates them as the market moves, for Islamabad and Rawalpindi. Costs can differ elsewhere. The date beside the result shows when they last changed.